Guide to obtaining location conditions and building permits
Location conditions, building and occupancy permits and legalisation — required documents, deadlines and application forms under the Law on Spatial Planning and Construction.
Documents — Spatial Planning Department
Building permit
The procedure for issuing a building permit under the Law on Spatial Planning and Construction is initiated by a written application from the investor.
The investor must enclose with the application:
- the location conditions;
- proof of resolved property-law relations;
- the technical documentation review report.
The investor also encloses the concession or public-private partnership agreement if a concession is granted or a public-private partnership agreement is concluded for the requested construction.
If the main design was prepared under the regulations of another country, the investor encloses a certificate of nostrification of the design.
Where necessary or required by other regulations, the investor also encloses with the building permit application an environmental permit or a decision approving the environmental impact assessment study.
As proof of resolved property-law relations, the investor encloses an extract from the public real estate register, or a contract or decision of the competent authority suitable as a basis for acquiring ownership or building rights in favour of the investor, or a joint construction agreement concluded with the owner of the land or property.
If the building land is owned by several persons, the investor must submit an extract from the public real estate register and an agreement on mutual relations between the investor and the co-owners.
On receipt of the application, the administrative body responsible for construction in the local self-government unit determines whether all required documents have been enclosed.
If the application has formal deficiencies or is incomplete, the competent authority will notify the investor and invite them to remedy the deficiencies and complete the application within a reasonable period; otherwise the application will be dismissed.
After receiving the application and before issuing the building permit, the competent authority will ask the investor to submit the decision setting the urban building land development fee and rent, together with proof of payment of the fee. If this obligation towards the local self-government unit has been settled in another way, the investor submits the agreement defining how it was settled.
Deadline, content and validity of the building permit
The competent authority decides on the building permit within 15 days at the latest from the completion of the application.
The building permit expires if works do not begin within 3 years of the date on which it became enforceable.
The investor must notify the competent urban planning and construction inspectorate of the start of construction no later than eight days before works begin.
The building permit contains details of the investor, the building for which it is issued, its use, footprint and number of storeys, the plot number, the title of the main design and the licensed legal entity that prepared it with the name of the chief designer, the technical documentation review report, a statement that the main design forms an integral part of the building permit, and the certification, signature and seal of the issuing authority.
After the permit is issued, the investor may apply to amend or supplement it.
Grounds for amendment or supplement are changes or additions to the technical documentation or main design, and changes affecting the position, use, structure, equipment, environmental protection, stability, functionality, dimensions or external appearance of the building.
Location conditions
Procedure for issuing location conditions
For individual residential and individual residential-commercial buildings with a gross floor area of up to 400 m², other than complex buildings within the meaning of the Law, built in an area covered by an implementing spatial planning document or outside urban areas, no location conditions are required to obtain a building permit.
The procedure for issuing location conditions under the Law on Spatial Planning and Construction is initiated by a written application from the investor.
The investor must enclose with the application:
- urban planning and technical conditions and an expert opinion if there is no implementing spatial planning document, submitted in three copies only if they are prepared outside the local self-government body responsible for spatial planning;
- a copy of the cadastral plan, or an up-to-date survey base for the proposed routes of linear utility infrastructure, certified by the authority responsible for surveying and cadastre;
- proof that the existing building is legal, in the case of an extension, an added storey or a change of use of an existing building;
- a description of the building;
- consents to the building location required by the urban planning and technical conditions under special laws depending on the type and use of the building (utility companies managing utility infrastructure, public companies managing public infrastructure and the like), if such consents are not contained in the urban planning and technical conditions;
- a decision determining the obligation to carry out an environmental impact assessment and its scope, if one is mandatory under a special regulation; and
- a conceptual design and proof of ownership of or building rights over the land, for buildings that do not require a building permit under this Law.
Exceptionally, if the area of future construction is covered by an implementing spatial planning document, the investor is not required to enclose the consents referred to in item 5.
If the area of future construction is covered by a valid available spatial planning document and the planned construction does not comply with it, the authority responsible for issuing location conditions must inform the applicant.
If the applicant has enclosed all required evidence and the planned construction complies with the valid available spatial planning document, the competent authority proceeds to prepare the location conditions.
If not all evidence has been enclosed, the competent authority invites the applicant to submit it within an additional period of no more than 30 days; otherwise the application will be dismissed.
Deadline, content and validity of location conditions
The competent authority must issue the location conditions within 15 days of receiving the complete application.
If the location conditions are not issued within the prescribed deadline, the investor may appeal as if the application had been rejected.
If the area of future construction is covered by an implementing spatial planning document, the location conditions consist of a certified extract from that document and the urban planning and technical conditions.
If the area of future construction is not covered by an implementing spatial planning document, the location conditions consist of:
- an extract from the valid available spatial planning document;
- an expert opinion and urban planning and technical conditions; and
- statements by the owners of neighbouring buildings and plots, obtained by the authority ex officio or by the investor with signatures certified by a notary.
Location conditions remain valid until the valid plan is amended or an implementing plan is adopted, where its adoption is mandatory.
If the investor has not applied for a building permit within one year of the location conditions being issued, before applying they must obtain a certificate that the location conditions issued have not changed.
The investor may apply to amend or supplement the location conditions if the requested changes concern the position, change of use, environmental protection or stability, functionality, dimensions or external appearance of the building and can be reconciled with the spatial planning document on which they were based.
Occupancy permit
The procedure for issuing an occupancy permit under the Law on Spatial Planning and Construction is initiated by a written application from the investor.
A completed building may not be used or put into service before the competent authority issues an occupancy permit by decision, following a technical inspection of the building.
The technical inspection must be carried out within 15 days at the latest of the complete occupancy permit application being submitted.
The investor, or the owner of the building or their legal successor, submits the occupancy permit application to the administrative body that issued the building permit once they and the supervising engineer have established that the building or part of it has been built in accordance with the building permit so that it can be used, and that an as-built design has been prepared where there have been changes that do not require an amendment of the building permit.
The applicant encloses:
- the building permit with the as-built design in two copies, if it was prepared and certified in accordance with Article 104 of the Law on Spatial Planning and Construction,
- a certificate of the geodetic survey of the building,
- proof of the survey of underground installations,
- consent to the as-built condition, where required by special regulations,
- the contractor’s statement on the works performed and the conditions for maintaining the building referred to in Article 60(2) of this Law,
- the supervising engineer’s report,
- the building’s energy performance certificate.
The technical inspection is carried out by an expert commission set up by decision of the authority that issued the building permit, within three days of receiving the complete application.
Commission members may be professionals in the relevant field licensed to review or prepare technical documentation or to carry out the works subject to inspection.
The competent authority may entrust the technical inspection to a legal entity licensed to review or prepare technical documentation or to build, provided that neither the entity nor its employees supervised or took part in the construction of the building.
Within eight days of the technical inspection, the commission must draw up a written report on the result of the inspection of the building or works, which includes the Minutes of the technical inspection.
The minutes contain the opinion of each commission member on whether the building can be used, whether identified deficiencies must first be remedied, or whether the occupancy permit cannot be issued.
If the technical inspection report finds no deficiencies, or that identified deficiencies have been remedied, the competent authority must issue the occupancy permit within eight days of receiving the minutes.
If the technical inspection identifies deficiencies that need to be remedied, the competent authority will order by decision that they be remedied within a set period.
If all deficiencies have been remedied, the competent authority issues the occupancy permit within eight days of the repeat technical inspection; otherwise a decision rejecting the occupancy permit application is issued.
The costs of the technical inspection are borne by the investor or owner of the building.
On the basis of the inspection commission’s opinion, the competent authority may issue a permit for trial operation and temporary use of the building during the trial period for a building that requires trial operation because of its technological process, installations, equipment and plant — but only if the commission has established that the building was built in accordance with the building permit and that trial operation does not endanger human life and health, the environment or neighbouring buildings.
Trial operation may last no more than one year; exceptionally, for particularly complex technological processes, it may be extended by a further year.
If damage to a building threatens the stability of the building or part of it, or if there is a danger to neighbouring buildings or to people’s safety, the owner must take urgent measures to remove the danger and mark the building as dangerous until the damage is repaired.
The owner may remove a building or part of it, unless removal is ordered by an inspection decision, only on the basis of a demolition permit.
The administrative body responsible for spatial planning, ex officio or at the request of an interested party, orders by decision the removal of a building or part of a building found, because of physical deterioration, natural disasters, war damage or major damage, to be no longer fit for its purpose and to pose a danger to human life or health, surrounding buildings and traffic, together with the conditions and measures to be implemented or ensured during removal, as established on the basis of the findings and opinion of an expert in the relevant field.
Legalisation
What is legalisation?
Legalisation within the meaning of the Law on Spatial Planning and Construction (Official Gazette of Republika Srpska No. 40/13) (hereinafter: the Law) is the subsequent issuing of location conditions, a building permit and an occupancy permit for buildings or parts of buildings built, started or reconstructed without a building permit, as well as buildings built under a building permit where construction departed from the permit and the main design, which were built or whose construction began before the Law entered into force.
Deadline for legalisation applications
Buildings built before the first aerial photogrammetric survey of the local self-government area, carried out by the end of 1980, are considered legally built.
Owners or investors who previously applied for legalisation under the regulations then in force are deemed to have applied under the Law, and the procedure will be concluded under whichever regulation is more favourable to the investor.
Legalisation procedure
The procedure for legalising an unauthorised building is initiated at the request of the investor or owner of the building.
The Spatial Planning Department carries out an on-site inspection within 30 days of the application and informs the applicant of the options for legalisation and of the evidence to be submitted to complete the application.
Completed buildings are legalised without the subsequent issuing of location conditions, unless this is needed to legalise a building built on state-owned land.
The planning basis for legalisation is the regulation plan or another implementing spatial planning document; where there is no such document, the planning basis is determined in accordance with the Law.
Exceptionally, for completed buildings that do not comply with spatial planning documents, if the building exceeds the planned number of storeys by no more than two floors, the top one being an attic, or departs by 10% from the planned horizontal footprint, legalisation may be carried out under conditions set by the Law.
The decision subsequently issuing a building permit for unfinished buildings is based on the evidence referred to in Article 128 of the Law.
For completed individual residential and residential-commercial buildings with a gross floor area under 400 m², other than complex buildings within the meaning of the Law, the subsequent building permit and occupancy permit are issued in the same decision.
For individual residential and residential-commercial buildings with a gross floor area under 400 m², other than complex buildings within the meaning of the Law, that are not fully completed but whose structure, roof and façade walls are finished, the building permit is issued with a reduced scope of technical documentation, as for fully completed buildings of this kind, and the occupancy permit is issued under the provisions of the Law.
Temporary retention of a building
An unauthorised building in use, or part of it, that cannot be permanently legalised under the Law is temporarily retained until the land on which it stands is brought to its final use under the regulation plan; the competent legalisation authority issues a decision to that effect.
For temporary retention, the documents prescribed by the Law are enclosed depending on the type and size of the building, on the basis of which the building may be connected to utility and public infrastructure.
For temporary retention the investor pays 20% of the legalisation fee calculated in accordance with the Law.
If, before the temporary period expires, a new implementing spatial planning document is adopted under which the building can be permanently retained, the fee paid for temporary retention is credited towards the fee for permanent legalisation.
Action by the urban planning and construction inspectorate
If a legalisation application has been submitted, the competent urban planning and construction inspector will, by a ruling, suspend enforcement of the decision to remove the unauthorised building, or part of it, built or started without a permit until the legalisation procedure is finally concluded.
When the legalisation procedure ends with a final rejection or dismissal of the application, the inspector will resume enforcement of the removal decision.
The competent inspector must initiate removal proceedings for an unauthorised building for which the investor has not applied for legalisation.
Buildings that cannot be legalised
A subsequent building permit cannot be issued if the building was built, reconstructed or extended:
- on land unsuitable for construction, such as landslide areas, marshland, or land exposed to floods or other natural disasters;
- from materials that do not ensure the durability and safety of the building;
- on public-use areas or on land planned for the development and construction of public-use buildings or areas for which a public interest is established under special regulations;
- in zone 1 of protection of a natural asset, or in the protection zone of a cultural asset of special importance or one included on the World Heritage List.